Completed before 2025
Turakurgan TPP — Yulduz substation 220 kV line
Construction of a 26 km 220 kV overhead line from the Turakurgan thermal power plant to the Yulduz substation.
- Region
- Namangan Region
- Status
- Completed before 2025
- Length
- 26 km
- Voltage
- 220 kV
- Client
- NEGU JSC

Services on this project
Other projects
All projects
Completed before 2025
Guzar-500 — Amir Temur (Azamat) 220 kV line
Double-circuit, 59.6 km · Kashkadarya Region
Learn more
Completed before 2025
Power supply for traction substations of the Pap — Namangan — Andijan railway
110 kV line and 220 kV in-out, 54 km · Namangan Region
Learn more
Completed before 2025
Chupon Ota 220 kV substation expansion and 220 kV line
Transformer T-5, 220 kV line, 40 km · Samarkand Region